The state organization, as the responsible executor of the program, shall submit a request to the land management organization for the formation of a land plot for the placement of a construction object.
The request shall specify:
- characteristics of the construction object, including information on its functional purpose and approximate dimensions;
- the intended location of the land plot and its approximate area;
- the volume of planned investments and sources of financing for the construction of the object.
The request shall be accompanied by an extract from the program or a corresponding decision of the President of the Republic of Belarus. The land management organization shall conclude a contract for the performance of work (term: 3 working days); shall prepare a land management case for the formation of a land plot, shall prepare a draft decision of the executive committee on the seizure of the land plot (term: 15 working days) and shall send them to the relevant land management service (term: 1 working day after the preparation of the land management case).
The land management service shall review the submitted land management case and the draft decision of the executive committee (clarifying it if necessary) and shall submit them to the relevant executive committee for a decision within its competence on the seizure and provision of the land plot (term: 5 working days).
The local executive committee shall make a decision on the seizure of the land plot for auction (term: 5 working days) and shall transfer the land management case for the formation of the land plot with the decision to the land management service (term: 3 working days),
The land management service shall send the land management case with the decision on the seizure of the land plot for auction to the land management organization (term: 1 working day).
The land management organization shall transfer the land management case to the state registration organization (term: 2 working days).
days) and shall transfer the land management case with the decision to the land management service (term: 3 working days).